Examining the Performance and Responsibility of Consulting Engineers in Advancing Construction Projects in Terms of Costs and Time Management (Intra-Urban Bridges in Mazandaran Province)

Authors

  • Ghasem Gorji Bandpey Department of Civil Engineering, Babol Noshirvani University of Technology, Babol, Iran.
  • Amirhossein Goleij Department of Civil Engineering, Ayatollah Amoli Branch, Islamic Azad University, Amol, Iran.

DOI:

https://doi.org/10.22105/9veaed38

Keywords:

Cost, Time, Project management, Consulting engineers, Bridge construction

Abstract

This research evaluated the performance and accountability of consulting engineers in optimizing cost and time management in intra-urban bridge construction projects in Mazandaran province. Classified as applied research with a descriptive survey methodology, the study focused on experts in construction projects due to their specialized knowledge. Key factors influencing project performance included material and labor procurement, on-site resource availability, workforce skill and productivity, stakeholder financial status, consultant and subcontractor expertise, economic and environmental conditions, contractor technology, site and design quality, management practices, and decision-making efficiency. The analysis revealed that factors such as resource availability, workforce productivity, subcontractor expertise, site conditions, and contractor management positively impacted cost and time efficiency. In contrast, delays in decision-making, rework, poor coordination, and environmental challenges were identified as constraints. The findings highlight the importance of addressing these factors to improve project outcomes.

References

Car-Pusic, D., Petruseva, S., Zileska Pancovska, V., & Zafirovski, Z. (2020). Neural network-based model for predicting preliminary construction cost as part of cost predicting system. Advances in civil engineering, 2020(1), 8886170. https://doi.org/10.1155/2020/8886170

Celik, Y., Petri, I., & Barati, M. (2023). Blockchain supported BIM data provenance for construction projects. Computers in industry, 144, 103768. https://doi.org/10.1016/j.compind.2022.103768

Chen, Z., Yuan, J., & Li, Q. (2017). Financing risk analysis and case study of public-private partnerships infrastructure project. Proceedings of the 20th international symposium on advancement of construction management and real estate (pp. 405–416). Springer. https://doi.org/ 10.1007/978-981-10-0855-9_35

De Marco, A., & Mangano, G. (2017). Risk factors influencing the debt leverage of project financing initiatives in the energy industry. International journal of energy sector management, 11(3), 444–462. https://doi.org/10.1108/IJESM-02-2017-0006

Gao, N., & Touran, A. (2020). Cost overruns and formal risk assessment program in US rail transit projects. Journal of construction engineering and management, 146(5), 5020004. https://doi.org/10.1061/(asce)co.1943-7862.0001827

Haaskjold, H., Andersen, B., & Langlo, J. A. (2023). Dissecting the project anatomy: understanding the cost of managing construction projects. Production planning and control, 34(2), 117–138. https://doi.org/10.1080/09537287.2021.1891480

Lock, D. (2007). Project management. Ashgate Pub Co. https://www.amazon.com/Project-Management-Dennis-Lock/dp/0566087723

Tirkolaee, E. B., Goli, A., Hematian, M., Sangaiah, A. K., & Han, T. (2019). Multi-objective multi-mode resource constrained project scheduling problem using Pareto-based algorithms. Computing, 101(6), 547–570. https://doi.org/10.1007/s00607-018-00693-1

Ballestín, F., & Leus, R. (2009). Resource-constrained project scheduling for timely project completion with stochastic activity durations. Production and operations management, 18(4), 459–474. https://doi.org/10.1111/j.1937-5956.2009.01023.x

Version, D. (2006). Time-constrained project scheduling Time-Constrained Project Scheduling. Journal of scheduling, 11, 137–148. https://doi.org/10.1007/s10951-008-0059-7

Hemmatian, M., Amiri, M. J. T., & Ghenaat, O. (2019). Presentation of exact and metaheurestic solution method for minimization project completion time with considering budget constraint problem. Journal of structural and construction engineering, 6(3), 41–56. (In Persian). https://dx.doi.org/10.22065/jsce.2018.104864.1377

Hazιr, Ö., Haouari, M., & Erel, E. (2015). Robust optimization for the discrete time-cost tradeoff problem with cost uncertainty. Handbook on project management and scheduling vol. 2, 865–874. https://doi.org/10.1007/978-3-319-05915-0_9

Lee, K. T., Park, S. J., & Kim, J. H. (2023). Comparative analysis of managers’ perception in overseas construction project risks and cost overrun in actual cases: A perspective of the Republic of Korea. Journal of asian architecture and building engineering, 22(4), 2291–2308. https://doi.org/10.1080/13467581.2022.2116940

Nabipoor Afruzi, E., Aghaie, A., & Najafi, A. A. (2020). Robust optimization for the resource-constrained multi-project scheduling problem with uncertain activity durations. Scientia Iranica, 27(1), 361–376. https://doi.org/10.24200/SCI.2018.20801

Choudhary, A. (2019). What are risk management techniques in project financing? https://www.lsbf.org.uk/blog/news/accountancy-finance/what-are-risk-management-techniques-in-project-financing

Yousefi, V., Golkhandan, A. R., Kiani, S., Yakhchali, S. H., & Mehrabanfar, E. (2015). Ranking of financing methods in Iran construction renovation projects: A sensitivity analysis approach. Mediterranean journal of social sciences, 6(5S2), 303–309. https://doi.org/10.5901/mjss.2015.v6n5s2p303

Pinto, J. M. (2017). What is project finance? Investment management and financial innovations, 14(1.1), 200–210. https://www.ceeol.com/search/article-detail?id=988329

Rauzana, A. (2016). The effect of the risk factors on the performance of contractors in Banda Aceh, indonesia. ARPN journal of engineering and applied sciences, 11(15), 9496–9502. https://ospro.usk.ac.id/article/google/3231014

Mahdi, I., & Soliman, E. (2021). Significant and top ranked delay factors in Arabic Gulf countries. International journal of construction management, 21(2), 167–180. https://doi.org/10.1080/15623599.2018.1512029

Amri, T. Al, & Marey-Pérez, M. (2020). Towards a sustainable construction industry: delays and cost overrun causes in construction projects of Oman. Journal of project management (Canada), 5(2), 87–102. https://doi.org/10.5267/j.jpm.2020.1.001

Ansell, C., Sørensen, E., & Torfing, J. (2022). Funding and financing local cocreation projects. In Co-creation for sustainability, emerald publishing limited, leeds (pp. 121–136). Emerald Publishing Limited. https://doi.org/10.1108/978-1-80043-798-220220009

Chapman, R. J. (2001). The controlling influences on effective risk identification and assessment for construction design management. International journal of project management, 19(3), 147–160. https://doi.org/10.1016/S0263-7863(99)00070-8

Taylan, O., Bafail, A. O., Abdulaal, R. M. S., & Kabli, M. R. (2014). Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Applied soft computing journal, 17, 105–116. https://doi.org/10.1016/j.asoc.2014.01.003

Published

2024-08-27

How to Cite

Examining the Performance and Responsibility of Consulting Engineers in Advancing Construction Projects in Terms of Costs and Time Management (Intra-Urban Bridges in Mazandaran Province). (2024). International Journal of Researches on Civil Engineering With Artificial Intelligence , 1(1), 95-102. https://doi.org/10.22105/9veaed38